top of page
ADP1.jpg

ADP

Sector

Finance

Location

 Staines, TW18

Year

2022

Size

47,500 sq/ft

Timeframe

12 Weeks

The Project overview

  • floors
  • 1000 Cat 6a outlets 
  • 72 multimode fibres
  • 3 Communications rooms
​
Background
 

Following ServiceIT Networking's successful appointment as the structured cabling contractor.

 

An  internal fitout across the tree floors was to be caried out and our responsibility was to provide both the backbone and all the horizontal cabling to the required design and specification allowing for diverse routes for both copper and fibre to multiple communications rooms

ADP3.jpg
ADP2.jpg
The Solution

​

Completing the installation was carried out floor by floor from top to bottom.  With an excellent design,  main contractor and project team this was a lovely projetc to work on and we were able to carry out the works within the timescales set and offer full manufacturers certification.

 

Key Partners 

​

  • Mayflex  
  • APC

Previous 

Next