The Project overview
-
1 floor
-
400 Cat 6 & 6a outlets
-
1 MER
Background
Following ServiceIT Networking's successful appointment as the structured cabling contractor.
Our responsibility was to provide all the horizontal cabling to the required design and specification to a single MER
The Solution
​
Completing the installation with several refurbishments taking place at the same time meant that one of the key challenges was always going to be logistics. With an excellent main contractor we were able to carry out the works within the timescales set and offer full manufacturers certification.
Key Partners
​
-